Operating principle of height limiter


When the construction of the lift cage upward operation, travel switch on the small roller in the concave point of the convex and concave pull - electric bearing. When the lift appears mechanical failure or operator misoperation, the lifting cage has been rising to the limit height, that is, lifting height limit device set height, because the lifting cage beam pulls the fine wire rope and convex and concave pull, together, the small roller on the travel switch due to external force to move up to the convex convex pull, the small roller from the mouth point electric bearing move to the convex point, so that the travel switch power off, Block the ascending power supply, the motor of the hoist stops working, and the lifting cage stops running. The convex and concave pull bar of the manual lifting height limit makes the small roller on the travel switch reset from the convex point to the electrified position of the concave point, so that the lifting cage can be started.


The equipment conforms to the requirements of "construction lift safety Rules". When the lifting cage is running beyond the set height, the device can quickly cut off the total power supply and make the lifting cage park. In the specification, it is emphasized that the SS elevator for both people and goods is not allowed to use active reset type, and the safety equipment is not active reset type. Block the total power supply when the action, manual reset after the action, rehabilitation of the power state, so that the lift normal operation, effectively avoid the occurrence of the "roof" incident.


Conclusion: The lifting height limit is novel, simple in structure, safe and reliable in active control, and can effectively control the occurrence of the "roof falling" incident by pulling it only once when avoiding the incident. And the manufacturing cost is low, it is worth implementing and using, the equipment is suitable for the construction of lifts, longmen frame, construction derrick and other kinds of vertical transport equipment.


How to debug height limit device


The debugging steps of tower crane lifting height limit are as follows:


1. The lifting height stopper should be adjusted under no load of the tower crane, and the micro switch should be separated from the pressure. Acknowledge the sensitivity and reliability of the two-gear lifting limit microswitch. When the micro switch corresponding to the CAM is pressed down, the power supply of the fast rising operation is blocked, and the lifting hook can only rise at a low speed. When the micro switch corresponding to the CAM is pressed down, the power supply of the lifting operation is blocked, and the lifting hook can only fall and not rise.


2. When the hook is raised in the meantime, make the vertical distance between the top and the bottom of the trolley be 1.3m or 1m, set the shaft 2Z, make the CAM 2T move until the micro switch 2WK is instantaneously changed, and tighten the nut.


3. Raise the lifting hook at a low speed so that the vertical distance from the top to the bottom of the trolley is 1 m or 0.7 m, set the shaft 1Z, make the CAM 1T action to make the micro switch 1WK instantaneous replacement, tighten the nut.


4. Repeated no-load verification and correction of the height limit of the two gears.



5. When the hoist pulley block ratio is changed, the height limit should be adjusted from scratch.



Recommend news
Tags

CONTACT

Enter your Emall or phone number and we will contact you as soon as possible.
ZORGON As a professional automatic control equipment manufacturer in the UK, with the first solenoid valve came into being, after decades of continuous innovation and development. With the transfer of...

Any question or request?

Click below, we’ll be happy to assist. CONTACT
© Copyright 1990 - 2023 | ZorGon| All Rights Reserved SiteMap